Construction to begin on Mullis Street, March 22

Submitted by the Town of Friday Harbor

“Local Access on Mullis Street from 818 Mullis St. to the Spring Street Intersection will be impacted while contractors reconstruct the road and install a roundabout,” said Administrator Wilson. “We ask the local businesses and their patrons for patience as we work through this necessary disruption.”

Traffic will be disrupted beginning March 22 through May 28 while the Contractor reconstructs Mullis Street. The contractor, Konnerup Construction, has been asked to expedite the project with as little traffic disruption as possible; however, road closures and detours will be unavoidable. Travelers should expect delays and limited or no access during certain phases of the project. The public is asked to exercise patience and to make every effort to be respectful of surroundings when using detours.

Information and updates on the project will be posted online as often as possible. Questions for daily operations can be directed to the Contractor, Justin Konnerup, Konnerup Construction 425-508-0847 or Project Inspector, Pedro Mena, Town of Friday Harbor at 360-378-2154.

As always, drive carefully and thank you in advance for proceeding with caution in areas where Crews are working in the roadway.

Project Description

Reconstruction of approximately 1,300 linear feet of Mullis Street from 818 Mullis St. (Guard Electric/Airport Property) to Spring Street. This project includes a cement-treated base, paving, ADA-compliant ramps and sidewalk, curb and gutter, and a painted roundabout at Spring Street. Plans and specifications are available at Town Hall for review.

Working Hours:

The contractor will begin mobilizing the week of March 22. Work is authorized Monday through Friday from 7 a.m. to 7 p.m. Typically, working hours will be a combination of four 10-hour workweeks with the exception of April 5 through April 16. Work will be substantially complete by May 28 (50 working days).

Street Closure

Northbound and Southbound lanes will remain open initially. There will be times when the contractor needs use of both lanes and vehicles may experience short delays. Expect up to 10-minute delays. Traffic will be diverted around the work or stopped entirely when necessary.

The Southbound lane will be closed for approximately two weeks beginning April 5th when heavy road construction takes place.

Limited parking will be permitted and determined on a day-to-day basis.

Local access will remain open at all times; however, neighbors of the project should anticipate short delays during certain portions of construction. Pedestrian access will be maintained. The Contractor is making every effort to not be disruptive to businesses in the area.

Detour

Flaggers will be on-site as needed. The designated detour routes are Market Street and/or Argyle Avenue depending on construction tasks. The detour routes will remain in effect for the duration of the project. The Contractor will have appropriate detour signage in place. The public is reminded that detour routes are considered part of the project zone.

Plan alternate routes and parking to avoid delays. The town recommends that vehicles traveling to or from the south end of San Juan Island consider using Argyle Avenue or intersecting with Douglas Road to downtown to help ease congestion and wait times on Mullis Street.

Safety

Pedestrians and motorists should exercise common sense and caution. Be aware of equipment, construction workers, trucks and construction materials. Make sure you are seen while moving within the job site and abide by flagger instructions.