Pocket Park update

Submitted by the Town of Friday Harbor

The Pocket Park is now beginning to take shape. Most of the underground work has been completed. This week, the bases for the paver borders, benches and sculptures will be formed and poured. As soon as those are completed and the weather permits, the crews will close the upper curb and install the large stormwater curb inlet, then commence placing the final concrete walks and paver surface.

Finally, the saw cut grid, benches, planting soils, irrigation and vegetation will be installed near the end of March and first part of April.

Staff photo/Hayley Day                                Construction of the park started on Feb. 20.

Staff photo/Hayley Day Construction of the park started on Feb. 20.